Activities/Work Currently In Progress At This Site:

·         EA study is proceeding.

 

Issue Currently Affecting This Site:

·         None.

 

Future Activities/Work Planned At This Site:

·         NEPA Status: Not Submitted. EA in progress.

·         IMPM to follow up on Site Overview Document with Facility Manager to obtain approval.

·         IMPM to create draft SOW, NEPA, Site Map, and Shelter Layout.

·         Waiting for BLM approval.

·         IMPM to start on next steps for procurement.

·         Local vs IM Procurement

·         Infrastructure (2% complete, 2009):

·         Tower

·         Shelter

·         Generator & Propane Tank

·         Electrical Work

·         Fence

·         Microwave hop to VC Pass (2009)

·         Microwave hop to Beaverhead EOC (2009)

·         Trunking (2010 or later)

 

Previous Activities/Work Completed At This Site:

·         Bob McWilliams (Beaverhead County and Facility Manager) has obtained a contractor to conduct the EA Study.  The study is scheduled to be completed September 30, 2008.

 

IM Project Managers For This Site:

·         Infrastructure (civil construction: towers, shelters, generators, etc.)

·         Primary: Tom Smith, (406) 443-8687, tom2.smith@ngc.com

·         Backup: Keith Lavender, (406) 443-8676, keith.lavender@ngc.com

·         Microwave

·         Primary: Dave Clouse, (406) 443-8663, dave.clouse@ngc.com

·         Backup: Mark Adams, (406) 443-8694, mark.e.adams@ngc.com