Sierra (Madison County) - Status Current As Of 7/18/2008
Activities/Work Currently In Progress At This Site:
· EA study is proceeding.
Issue Currently Affecting This Site:
· None.
Future Activities/Work Planned At This Site:
· NEPA Status: Not Submitted. EA in progress.
· IMPM to follow up on Site Overview Document with Facility Manager to obtain approval.
· IMPM to create draft SOW, NEPA, Site Map, and Shelter Layout.
· Waiting for BLM approval.
· IMPM to start on next steps for procurement.
· Local vs IM Procurement
· Infrastructure (2% complete, 2009):
· Tower
· Shelter
· Generator & Propane Tank
· Electrical Work
· Fence
· Microwave hop to VC Pass (2009)
· Microwave hop to Beaverhead EOC (2009)
· Trunking (2010 or later)
Previous Activities/Work Completed At This Site:
· Bob McWilliams (Beaverhead County and Facility Manager) has obtained a contractor to conduct the EA Study. The study is scheduled to be completed September 30, 2008.
IM Project Managers For This Site:
· Infrastructure (civil construction: towers, shelters, generators, etc.)
· Primary: Tom Smith, (406) 443-8687, tom2.smith@ngc.com
· Backup: Keith Lavender, (406) 443-8676, keith.lavender@ngc.com
· Microwave
· Primary: Dave Clouse, (406) 443-8663, dave.clouse@ngc.com
· Backup: Mark Adams, (406) 443-8694, mark.e.adams@ngc.com
· Trunking
· Primary: Mark Adams, (406) 443-8694, mark.e.adams@ngc.com
· Backup: Keith Lavender, (406) 443-8676, keith.lavender@ngc.com
·
![]()