Virginia City Pass (Madison County) - Status Current As Of 7/18/2008

 

Activities/Work Currently In Progress At This Site:

·         Finalize the SOW and obtain Facility Manager Approval.

·         NEPA was rejected by FEMA. Must be resubmitted with IB 271 information. IMPM waiting for directions on next steps regarding impact of the FEMA requirement for the IB 271.

 

Issue Currently Affecting This Site:

·         None.

 

Future Activities/Work Planned At This Site:

·         IMPM to start on next steps for procurement.

·         Local vs IM Procurement

·         Waiting for BLM approval.

·         Infrastructure (12% complete, 2009)

·         Tower

·         Shelter

·         Generator & Propane Tank

·         Electrical Work

·         Fence

·         Microwave hop to Sierra (2009)

·         Microwave hop to Sawtell (2009)

·         Trunking (2010 or later)

 

Previous Activities/Work Completed At This Site:

·         NEPA Status: Rejected.

 

IM Project Managers For This Site:

·         Infrastructure (civil construction: towers, shelters, generators, etc.)

·         Primary: Tom Smith, (406) 443-8687, tom2.smith@ngc.com

·         Backup: Keith Lavender, (406) 443-8676, keith.lavender@ngc.com

·         Microwave

·         Primary: Dave Clouse, (406) 443-8663, dave.clouse@ngc.com

·         Backup: Mark Adams, (406) 443-8694, mark.e.adams@ngc.com

·         Trunking

·         Primary: Mark Adams, (406) 443-8694, mark.e.adams@ngc.com

·         Backup: Keith Lavender, (406) 443-8676, keith.lavender@ngc.com


·